OBSEON TRADING HOUSECanadian bitumen supply to East Africa
Logistics

Refinery to port in six stages

One contract of sale, one counterparty, from refinery gate to port of discharge.

  1. Origin procurement

    5–10 days

    Grade, tonnage and lifting window fixed with the refiner; batch certificate of analysis issued.

  2. Drumming & marking

    5–8 days

    Filled, cooled, sealed, weighed and marked with grade, batch, weight and origin.

  3. Pre-shipment inspection

    1–2 days

    Independent surveyor checks quantity, drum condition and samples.

  4. Inland haulage & stuffing

    2–4 days

    Trucked to a Canadian port and loaded into containers.

  5. Ocean carriage, CIF

    29–38 days

    Bill of lading issued in Canada. Insured at CIF value + 10%; route reviewed before each fixture.

  6. Discharge

    2–4 days

    Mainly the Port of Djibouti; documents prepared before arrival so clearance stays off the critical path.

Covered warehouse with bitumen drums and a forklift
Commercial terms

Standard terms

CIFNamed East African port, mainly Djibouti
LCIrrevocable, at sight, confirmed
1,000 MTMinimum order
180 kgNew steel drums
< 50 daysTarget, LC confirmation to delivery
110%Of CIF value insured
  • ProductBitumen, mainly 60/70 (ASTM D946 / AASHTO M20)
  • IncotermsCIF, Incoterms 2020. DAP to named sites on request
  • PaymentIrrevocable LC at sight, confirmed by a bank acceptable to the seller
  • Price validityFixed period, subject to freight and origin market movement
  • InspectionIndependent at origin; at destination at buyer's option and cost
  • Financed projectsOrigin, eligibility and chain-of-custody documents supplied; milestones aligned to disbursement

All terms can be discussed. Nothing is quoted until we are confident the shipment can perform.